Difficulty Level: Easy
Stats: 1,746 / 2,500
( 69.84% ) got this right
Slim can do 1/4 of an amount of work in 10 days. Pam can do 40% of the same work in 40 days. Melba can do 1/3 of the work in 13 days. Lastly, Little Jim can do 50% of the work in 19 days. Who will complete the work first?
- Slim
- Pam
- Melba
- Little Jim